It all flows downhill - Factory Drainage

25/5/2016

0 Comments

 
Once Drainage & Flooring have been installed, it is very hard to change, so it is critical that all drainage & floor slopes are specified and installed to meet current & expected future processes. We hear too many horror stories about water pooling or running away from drains yet the irony is that it costs no extra money to get it right in the first place!

2 main types of floor drains - Pit drains & Strip drains. While strip drains seem to be an ideal solution for quick wash-downs,  they do present hygiene issues that you need to be aware of which may make them unsuitable in rooms that are High Care or High Risk areas.
Picture
Pit Floor Drain
Picture
Strip Drain
Drain locations are critical - in terms of locality to equipment and water points. Drain locations must be well thought through to allow for pit drains to take water away from specific drain points, such as CIP drain valves or cooker drains.

With the correct floor slopes - enough for water to fall away but not steep enough to make traversing the room difficult - there will be no water pooling on floor surfaces. Floor slopes can be configured such that strip drain locations have been considered not suitable, pit drains can be successfully utilised in their place. Slopes will typically range from 1:50 to 1:100. We aim for around 1:80 where possible.
Picture
Example of a hydraulics / Drainage drawing
To meet High-Risk & High-Care requirements of retailers and local water authorities, there are specific details in the hydraulic design that need to be incorporated. RMR Process can assist with achieving this compliance.

The last consideration for drainage is the water temperature, flowrates & chemicals going down the drain and the effects of these variables on each component.

Should you require any assistance on any of the details above, please contact RMR Process - we can help weave a path through the minefield that is drainage.
0 Comments

    Author

    K Prelovsky, RMR Process.

    View my profile on LinkedIn

    Archives

    January 2020
    September 2019
    August 2019
    February 2019
    January 2019
    November 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    February 2016

    Categories

    All
    Article
    Automation
    Conference
    Drainage
    Export
    Floors
    High Care
    High Risk
    Manual Handling
    Packaging
    Process Improvement
    Projects
    Retorts
    Scaling Up
    Scoping
    Wicked Sister

    BLOG

RMR Process Pty Ltd
"KEEPING FOOD MANUFACTURING ALIVE IN AUSTRALIA & NEW ZEALAND"
Contact us now +61 3 9023 9130 or info@rmrprocess.com
RMR Process Pty Ltd
​Melbourne, Australia
Copyright © 2016
  • Home
  • Our Story
    • Our Story
    • Why our model works
  • Gallery
  • Projects
  • News
  • Contact
  • YouTube
  • CAREERS AT RMR